Friday, January 15, 2010

Day 100

We have officially reached Day 100 (as of 13-1-10) of our build (only 265 days to go hehe...).

The upstairs render is now complete and ready to be painted (Paperbark).





The 1st Fix plumbing started on 14-1-10.





We noticed they have put the back external tap in the wrong position, so hopefully they will respond to our email and relocate it. Should be an easy enough fix.

The next stage is LOCK-UP.

2 comments:

Vundaful said...

Lookin' good, coming along nicely :D

TamDaz said...

Thanks Vundaful, your house is comming along well too. You have been very busy the past week updating your blog to your current progress. Your technical skills (helping colour edit TM's facade, and the 360 views of your land, slab, living area) are awesome. Would love to have those kind of skills myself. Thanks for checking in on my blog :-)