Monday, January 25, 2010

LOCK-UP

As of Tuesday 19-1-10, we have been locked up and locked out. I have photos of the temporary doors and a new tap at the front of the house, but apart from that I have not been able to take pics of anything else new. From my understanding, the 1st Fix internal plumbing is now complete and the air conditioning is soon to follow. We received our variation today for all the Electrical work, so will spend some time Australia Day going through it with a fine tooth comb. Hopefully is it finally all sorted so we can sign and get that ball rolling. Will post a photo of our 'lovely' doors soon. In the meantime HAPPAUSTRALIA DAY!

Friday, January 15, 2010

Day 100

We have officially reached Day 100 (as of 13-1-10) of our build (only 265 days to go hehe...).

The upstairs render is now complete and ready to be painted (Paperbark).





The 1st Fix plumbing started on 14-1-10.





We noticed they have put the back external tap in the wrong position, so hopefully they will respond to our email and relocate it. Should be an easy enough fix.

The next stage is LOCK-UP.